Keiler Terminal Station
B1 Transformer Enclosure and Monopole Footings
Contract Sum: $500,000 Client: Powercor Network Services/ SP AusNet
Description:
Multiworks inherited the second stage at Keilor Terminal Station following the insolvency of the previous contractor. Whilst relatively simple in nature; the works where required to be completed in a tight timeframe. Encountering both unstable soil conditions and working around the existing transformer base provided unique challenges to the project. Multiworks however, where able to successfully deliver the foundation on time for the delivery of the new transformer.
The scope of works included: