Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the breadcrumb-navxt domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/1267421.cloudwaysapps.com/hbhctqpqww/public_html/wp-includes/functions.php on line 6114
Austrim Nylex Decontamination | Multiworks Austrim Nylex Decontamination | Multiworks
This 4.5 hectare site in Coburg was originally used by Austrim Nylex for the manufacturing of plastic automotive components. Prior to the creation of a new public access road and subdivision into 36 industrial allotments, the site required extensive remediation of the contaminated soil and groundwater. The remediation process involved:
  • Removal and disposal of 30 underground storage tanks and associated product lines.
  • Removal of asbestos and demolition of approximately 5,000m2 of disused industrial buildings.
  • Excavation, remediation and reinstatement of over 40,000m3 of contaminated soil.
  • On site crushing and recycling of all concrete.
  • Facilitation and supervision of contaminated ground water with vacuum enhanced extraction technology.
  • Installation and commissioning of active skimming pumps
Location

Coburg, Victoria

Client

Tenya Pty Ltd

Completion

2007

Service

Civil Construction, Asset Security and Maintenance, Asbestos & Environmental Remediation

Sector

Industrial & Manufacturing

Value

$5M