Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the breadcrumb-navxt domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/1267421.cloudwaysapps.com/hbhctqpqww/public_html/wp-includes/functions.php on line 6114
FORD - Geelong | Multiworks FORD - Geelong | Multiworks

This historic project comes about as Ford Australia sells its manufacturing plants, bringing to a close more than half a century of Australian motoring history and local car production. The project scope included civil, structural, mechanical, commissioning and HV electrical works required for the separation of common building utilities for the subdivisions of the sites.

Multiworks was originally engaged through ECI to provide input into the design constructability, methodology, staging and scheduling of the proposed subdivision projects at Geelong and Broadmeadows. After a formal RFQ Multiworks was eventually engaged as Principal Contractor, responsible for managing and coordinating the entire scope and the site of up-to 120 people.

At Geelong, the new services to be constructed within the existing manufacturing site include domestic water, sewer, fire services and stormwater buried up-to 6 meters deep.

Work onsite was consistently challenged by subsurface conditions as contaminated and erodible soil was spread throughout the site. As principal contractor Multiworks both managed and self performed the remedial works ensuring the safety of those onsite and the environment was not placed at risk.

Location

Geelong, Victoria

Client

Ford/Aecom

Completion

2020

Service

Civil Construction, Asbestos & Environmental Remediation

Sector

Water

Value

$31M