Multiworks was responsible for the remediation and conversation of the 15 hectare James Hardie asbestos processing facility. The conversion of the site into a industrial park was undertaken over 7 years and required special care in not disturbing the underlying contamination. The works included;
- Installation of approximately 20,000m2 of geotextile fabric.
- The importation and compaction of approximately 150,000 tonnes of engineered fill.
- Construction of 3,500m2 of reinforced concrete road pavement.
- Spreading and compacting of 10,000 tonne of recycled concrete hardstand.
- Construction of 7,000m2 of engineered concrete hardstand
- Significant drainage, electrical and landscaping works.
Multiworks now has since managed and maintained the buildings and land.