Multiworks was responsible for the remediation and conversation of the 15 hectare James Hardie asbestos processing facility. The conversion of the site into a industrial park was undertaken over 7 years and required special care in not disturbing the underlying contamination. The works included;

  • Installation of approximately 20,000m2 of geotextile fabric.
  • The importation and compaction of approximately 150,000 tonnes of engineered fill.
  • Construction of 3,500m2 of reinforced concrete road pavement.
  • Spreading and compacting of 10,000 tonne of recycled concrete hardstand.
  • Construction of 7,000m2 of engineered concrete hardstand 
  • Significant drainage, electrical and landscaping works.
Multiworks now has since managed and maintained the buildings and land.
Location

Brooklyn, Victoria

Client

Cawley Road

Completion

Present

Service

Civil Construction, Asset Security and Maintenance, Asbestos & Environmental Remediation, Building

Sector

Industrial & Manufacturing

Value

$13M