Electricity -

MEL04 Datacentre

MEL04 is a state-of-the-art data centre located in Melbourne, designed to meet the growing demand for secure, reliable digital infrastructure. The facility provides significant power capacity to support critical data operations, ensuring high levels of performance and resilience for its users.

Multiworks was responsible for delivering the civil works for the substation at MEL04, including the construction of 3 transformer bays, fencing, foundations, stormwater drainage, and overground services. The project required an accelerated schedule, with the transformer bay completed within 10 weeks of commencement, allowing for the timely delivery of the transformer to begin commissioning.

Koorangie Battery Energy Storage (BESS)

Located 300km north-west of Melbourne’s CBD, the Koorangie BESS, developed by Edify Energy, will be connected to AusNet’s 220kV transmission network and provide system strength to the Murray River Renewable Energy Zone (REZ).

Our scope included the construction of foundations for the Tesla Megapack batteries, as well as the installation of associated conduits and critical infrastructure to support the 185 MW/370 MWh system. The project required meticulous coordination to meet stringent timelines, ensuring the battery foundations were completed and ready for the Tesla Megapacks to be installed on schedule. These foundations are integral to the performance of the grid-forming inverters, which will help stabilise the energy grid and increase the region’s renewable hosting capacity by up to 300 MW.

Altona Zone Substation

Multiworks was engaged by Powercor to upgrade the perimeter fence at the Altona Zone Substation, a critical infrastructure facility. The existing fence, in poor condition, posed security risks, prompting the need for an upgrade to enhance safety and protect the substation from unauthorised access. This project involved substantial civil, electrical, and safety considerations, complicated by challenging site conditions and tight constraints.

SCOPE

  • Removal of Existing Fence and Gates: Dismantling and removal of the old chain-link fence and gates, which were no longer providing adequate security.
  • Installation of New Perimeter Fence: Installation of a new 235m long, 3.5m high 358 Weldmesh galvanised perimeter fence.
  • Automated Entry Swing Gates and PA Gates: Installation of secure automated swing gates for vehicular entry, along with personnel access (PA) gates.
  • HV and LV Conduit Installation: Installation of high-voltage and low-voltage conduits to support updated electrical systems and future-proof the site.
  • Asphalt and Concrete Works: Construction of an asphalt entrance and a main concrete entrance slab to provide durable, safe points of access to the substation.

CHALLENGES

  • Ground Water: High groundwater levels necessitated careful planning and mitigation measures to ensure safe excavation and construction processes.
  • Rock: The abundance of rock on-site required extensive rock excavation, particularly near live services, which led to major redesigns.
  • Live Services: Proximity to vital live electrical services added complexity to the excavation and installation work, requiring heightened safety precautions and continuous monitoring.
  • Site Constraints: Limited space on-site impacted logistics and access for machinery and equipment, requiring creative solutions to maintain project efficiency.

ACHIEVEMENTS

  • Safety: The project was completed without any safety incidents, demonstrating Multiworks’ commitment to maintaining a safe working environment throughout the project lifecycle.
  • Quality Assurance: No quality issues were reported, ensuring that all work met Powercor’s high standards and specifications.
  • Timely Completion: Despite the challenging conditions, including the need for major redesigns, the project was completed on schedule, meeting all deadlines and exceeding client expectations.

M2 Datacentre

M2 Melbourne is a Tier IV certified data centre situated in Tullamarine, conveniently located near major transport and telecommunications infrastructure. Boasting 60MW of power capacity, M2 provides organizations with unparalleled levels of resilience, reliability and inter-connectivity.

Multiworks were responsible for the construction of the Datacentre Substation, involving all associated transformer bays, fencing, foundations, stormwater drainage and underground services.

Adding to the complexity of the project was the security requirements for entry, which are paramount at most Datacentres. Multiworks’ staff and all personel were responsible for ensuring no unauthorised entry to the site and adhered to stringent site rules.

Kerang Concrete Package

British Solar Renewable (BSR) initiated the Concrete Package at the Kerang Solar Farm which is Australia’s largest integrated battery and solar farm, home to a 50-megawatt battery that stores 100% renewable energy and feeds directly into the state’s electricity grid. Multiworks, working under British Solar Renewables, were responsible for the civil works associated with this project including footings, landings and piers.

SCOPE

Multiworks provided civil construction and project management services to deliver the Kerang Concrete Package. The scope involved:

  • 19 reinforced concrete stair landings
  • 13 deep reinforced concrete piers
  • A reinforced concrete transformer base
  • A reinforced concrete generator slab

CHALLENGES

  • The project posed multifaceted challenges, spanning survey, groundwater management, reinforced cages design, including access, drainage, and earthwork benches.
  • The project also faced intense timeline constraints as project award to project completion was an extremely quick turnover.
  • Work was required to be completed in time for the arrival of the Switchroom.

ACHIEVEMENTS

  • Despite the need for a quick turnover and immediate mobilisation to regional Victoria, the project was completed on schedule, demonstrating our ability to manage and execute projects efficiently.
  • We maintained a flawless safety record with zero incidents throughout the project duration.
  • The quality of our work was praised with no defects reported, reflecting Multiworks dedication to high standards.
  • Due to the Clients satisfaction with our work, the Scope was extended for additional concrete works.

Beryl & Mount Piper Containment Tanks

The Beryl and Mount Piper Substations contain 132/66kV networks to supply the local townships. Due to the aging condition of the existing transformer bunds a new containment system was required to allow for the containment of water and oils should there ever be a fault with the transformer. Multiworks provided all upgrade works at the two substations to upgrade this existing oil containment system. This involved the construction of new primary spill oil tanks, upgrade of existing bunds, installation of new connecting pipework for both substations and flame traps for Mount Piper only.

Adding to the complexity of this scope was the proximity of the proposed containment systems to the adjacent high-voltage and in-service electrical equipment. Multiworks took over the design of this element to create a piling retention system adjacent to the structures and to ensure the site remained operational through the work.

Narrabeen Control Building Roof Replacement

The Narrabeen Substation Control building houses the live electrical switchgear and equipment that control the adjacent substation. As part of the upgrade of ageing assets, Multiworks was engaged directly by Ausgrid as Principal Contractor to replace the existing roof while maintaining the live operations of the substation and the electrical network. The works included: replacement of roof tiles with Colorbond sheets, installation of CFC sheets, replacement of gutters, installation of new downpipes, installation of earthing spires and installation of new anchor points.

Prior to commencement of the roof replacement works the Narrabeen Control Building was impacted by a storm causing leakage inside the Switch-rooms. Ausgrid engaged Multiworks to execute emergency works to stop the leakage. This required the roof replacement works to be brought forward and delivered within a significantly constrained time frame.

Multiworks effectively mobilised a skilled team including additional resources from interstate. Due to the poor condition of the existing roof, Multiworks made the entire control room building watertight through implementing anchor points and tarping. This provided a temporary shield around the whole building, eliminated any impacts due to poor weather and ensured the ongoing operation of the control room.

Multiworks delivered the project one month ahead of schedule, while also completing the Castle Cove Substation works.

Castle Cove Control Building Roof Replacement

Multiworks was responsible for the replacement of roof metal sheets with Colorbond sheets, replacement of gutters, installation of new downpipes, construction of stormwater inlets and installation of new anchor points. Multiworks delivered all scope while ensuring the ongoing operations of the live electrical substation.

A key challenge in the roof replacement works involved implementing appropriate physical protection over the existing Frequency Injection Units (FIUs). Due to the sensitivity of the assets and client requirement that only one FIU could be de-energised at a time, Multiworks developed and implemented a staged works program over the FIUs. Multiworks effectively planned and scheduled materials and resources to ensure protection over the unit while replacing the section of roof directly above. The protection was then stripped so that the FIUs could be re-energised.

Additionally, Multiworks developed an innovative ‘Rolling Scaffold’ within the substation that offered fall protection and acted as a physical barrier to ensure the substation equipment was not exposed to falling objects.

Chullora Control Building Roof Replacement

The Chullora Substation Control building houses the live electrical switchgear and equipment that controls the adjacent substation. As part of the upgrade of ageing assets, Multiworks was engaged as Principal Contractor directly by Ausgrid to replace the existing roof without any interruptions to the electricity network.

Works took place on the existing live control building, housing equipment for this 66kV Substation. Key scope involved ACM eave replacement, removal of roof tiles, installation of two layers of Compressed Fibre Cement sheets, installation of Colorbond sheets, reinstating existing gutters, installation of new downpipes and installation of new anchor points.

During the preliminary planning, it was noted that the height from the pitch of the roof to the soffit was greater than 0.8m. Due to the substantial height difference the existing anchor points could not be used as a means of fall arrest. As a result, Multiworks proposed and successfully implemented a construction methodology that provided a means of fall arrest utilising anchor wraps. The project achieved zero safety incidents.

Lilydale Substation REFCL

The Victorian Government has mandated the rollout of Rapid Earth Fault Current Limiter (REFCL) installations across nominated Zone Substations in AusNet Services’ network, including at the Lilydale Zone Substation. Installation works included:

  • Two new REFCL(s) units in bunds and footings
  • Two new 22kV switched neutral bus kiosks onto new footings
  • A new REFCL Room on to new pad footings to house associated inverters and control equipment
  • A new modular Control Room onto new striped footings
  • A new cable trench (600mm Wide x 600mm Deep) running north west to south east for associated control cables Conduits for control cables
  • Associated reinstatement and surfacing

Replacement works involved:

  • The existing NER with one new NER onto new pad footing
  • Existing station service transformers (SSTx) with two new 750 kVA kiosk type units onto new pad footings and AC changeover boards
  • Both existing Capacitor Banks with Metal enclosed Cap Banks with pad footings for REFCL compliance.