Oil & Gas -

Viva Storage

VIVA Energy initiated the Strategic Storage Project to construct four new tanks capturing 90 million litres of diesel storage as part of the Federal Government’s plans to boost Australia’s Diesel Storage Program. Multiworks, working under mechanical and tank builder Brockman Engineering, were responsible for all civil works associated with this project including bulk earthworks, remediation, tank foundations and over 1,000m of concrete in-situ bund wall over 4m in height.

Works included

  • 1km bund wall over 4m in height
  • Major earthworks associated with the 62,500m2 area within the bund
  • Remediation of significant volumes of contaminated soils
  • Tank foundations
  • Concrete in-situ bund walls over 4m in height
  • Footings, pits and drainage
  • Roads and paving
  • Construction of access ramps, bund sumps
  • External roads in the ‘Greenfield’ area

The project posed multifaceted challenges, spanning tank foundations, concrete bund walls, pipe supports, and a wide range of civil works, including access ramps, drainage, and roads. The project also faced intense timeline constraints as work was required to be completed in time for the government subsidy to be obtained. Despite a significant increase in the scope, namely in contaminated soil remediation, Multiworks was able to accelerate the program by over 2 months.

Tullamarine Airport JUHI

Multiworks were engaged directly by Exxon Mobil as principal contractor to assist in the remediation works of the JUHI Tankage Site adjoining the Tullamarine Airport. The work was of critical nature as it involved working around the live infrastructure providing fuel to the Melbourne Airport. Multiworks was commended by Exxon for being able to mobalise and complete works within 5 weeks of commencement.

Works include, but are not limited to the following:
  • Bulk Earthworks for new Roads & Pavements
  • Upgrade of Stormwater Drainage including pits, pipes, geotextile lining & culverts
  • Construction of new crushed rock hardstand